![]() |
Hong Kong Law Reform Commission |
6.1 In this chapter, we shall look at the various minimum sales
particulars that should be provided by developers in sales brochures. We shall
review some of the recommendations made in the First Report and try to see if
they can be adapted for use in respect of completed units offered for sale by
developers in the first-hand market. In the process, we shall also put forward
ideas additional to those made in the First Report. As the First Report was
completed several years ago, some of the ideas useful at that time may have been
rendered obsolete.
6.2 Where prospective purchasers are not able to inspect the
completed units, they may have to rely on the descriptions contained in the
floor plan. This is the case even where mock-up or show flats are available for
them to view. Where purchasers can inspect the actual completed units, they may
still refer to the floor plans in the sales literature for a rough idea of the
internal layout and measurements.
6.3 We consider that all of the First
Report’s recommendations on floor plans of local uncompleted properties
are equally applicable to the sale of completed units by
developers.[67] However, the
requirement that a note be put in sales brochures to bring purchasers' attention
to the usual term in the formal ASP concerning the adjustment in purchase price
in proportion to variations in saleable area (arising from amendment to the
building plans) is not applicable in the context of completed units. It seems
unlikely that there would be any further change in the building plans as the
properties would have already been completed at the time they are offered for
sale.
6.4 The First Report recommended that there should be a legal
obligation on developers upon completion to inform purchasers of the saleable
area as certified by an
architect.[68] We consider that
developers should be under a similar legal obligation in respect of completed
properties, as the saleable area of a completed property is readily
ascertainable. We take the view that the saleable area quoted by developers
upon completion should be that supplied by the Authorised
Person.
6.5 The consultation paper recommended that floor plans in sales
brochures should be “presented according to conventionally accepted
scales”. Some respondents considered that “presented according to
conventionally accepted scales” was too vague and open to different
interpretations. One submission suggested that “drawn to scale and
reasonably legible” should be used instead. We agree with the suggestion
and have adjusted the original recommendation accordingly.
|
Recommendation 14 We recommend that: (1) The sales brochure should contain floor plans which: (a) specify the external dimensions of individual units; (2) The sales brochure should also contain: (a) schedules listing the saleable area of the unit and of any bay window areas, roof areas, flat roof areas, open yard areas, air-conditioning plant within the building, etc; and (b) a note that the internal area of units on the upper floors may be slightly greater than that of the lower floors, if that is the case. (3) Certified copies of the latest approved building plans should be made available for free inspection at the sales office during normal office hours. (4) There should be a legal obligation on the developer upon completion to inform purchasers of the saleable area (as provided by the Authorised Person). |
6.6 The quality of fittings and finishes of the individual unit and
of the common parts of a building is of considerable importance to purchasers of
residential properties. For people buying flats for their own occupation, good
quality fittings and finishes will mean a better living environment and less
money to be spent on maintenance and renovation. For those buying residential
properties for investment purposes, high quality fittings and finishes in
general enhance the letting and resale value of the property.
6.7 It is not always the case that purchasers of completed properties
can see for themselves the quality of fittings and finishes. Prospective
purchasers will therefore place great reliance on the descriptions of fittings
and finishes contained in the sales brochures. However, sales brochures do not
always contain uniform adequate descriptions of fittings and finishes. Most
sales brochures give only a general description of the fittings and finishes of
the individual units and of the common areas.
6.8 In its First Report, the Commission made some recommendations in
respect of fittings and finishes for local uncompleted residential
properties.[69]
6.9 These
recommendations were largely modelled on the list of fittings and finishes
contained in the Land Office Circular Memorandum No 101 (LOCM 101). On
28 May 1999, the Legal Advisory Conveyancing Office Circular Memorandum
No 40 (LACO CM 40) replaced LOCM
101[70]. LACO CM 40 contains
essentially the same disclosure requirements as had been imposed by the
superseded LOCM 101. LACO CM 40 is reproduced at Annex II of this report.
LACO CM 40 contains a list of fittings and finishes. The items are external
walls, windows, bay windows, planters, verandah/balcony, drying facilities for
clothing, lobbies, internal walls and ceilings, floors, bathrooms, kitchens,
doors, bedroom fittings, telephone and aerials, electricity fittings,
gas/electricity supply, washing machine connection point, water supply and
pipes, security facilities, lifts, letter boxes, refuse collection and water,
and electricity and gas meters.
6.10 We take the view that if prospective purchasers are given the
opportunity to inspect the completed units before entering into a preliminary
sale and purchase agreement so that they can verify the make and quality of
fittings and finishes on the premises, there is no need to change existing
requirements as to the contents of the sales brochure with regard to fittings
and finishes, save that those contents should not be misleading.
6.11 We consider it appropriate to extend the First Report’s
recommendations to local completed properties if there is no right of inspection
before entering into a preliminary sale and purchase agreement. In addition,
photographs of the fittings should be included in the sales
brochure.
6.12 Clearly, the provision allowing developers to use
substitute materials is not necessary for completed units, since at the time of
printing of the sales brochures the intended materials should have already been
used.
6.13 Though developers had reservations about stating brands and
origins of fittings and finishes to be used for uncompleted properties because
of possible changes in market provision, this should not be a problem in the
case of completed properties.
6.14 We take the view that photographs of
the fittings and finishes should be shown in the sales brochure. This will give
prospective purchasers some impression of the fittings and finishes in the
absence of a right to inspect the units offered for sale.
|
Recommendation 15 We recommend that where there is no right of inspection before entering into a preliminary sale and purchase agreement, the sales brochure should contain: (i) at least details of the fittings and finishes as stated in Appendix XII B of Legal Advisory Conveyancing Office Circular Memorandum No 40 (LACO CM 40); The sales brochure should also state the brands and countries of origin of the fittings and finishes to be used. In addition, photographs of the fittings and finishes should be shown in the sales brochure. |
6.15 Problems may arise because of occasional discrepancies between
the descriptions of the fittings and finishes contained in the Chinese and
English versions of the sales brochure. The First Report recommended for local
uncompleted residential properties that "if there are discrepancies between
the Chinese and English versions of the specifications of fittings and finishes
in the sales brochure, purchasers can choose which of the language versions is
applicable."[71] This
recommendation’s rationale was that the developer would be in a better
position than the purchaser to check the accuracy of the different language
versions. We consider that a similar approach should be applied to completed
residential properties.
|
Recommendation 16 We recommend that if there are discrepancies between the Chinese and English versions of the specifications of fittings and finishes in the sales brochure, purchasers can choose which language version they rely on. |
6.16 In order to avoid the inconvenience of letting a great number of
prospective purchasers inspect the completed units, mock-up or sample flats are
often used to show the quality of fittings and finishes. In the First Report,
the Commission took the view that it was unreasonable to oblige developers to
build mock-up flats. If developers chose to set up mock-up flats, however, they
had to accurately reflect the materials to be used. On this basis, the
Commission made the following recommendations in respect of local uncompleted
residential properties:[72]
"If mock-up or sample flats are provided, the mock-up should be accurately representative of the actual unit in all aspects including quality and dimensions and the Authorised Person of the development project should certify a schedule of the specifications of the mock-up flats. The developer should have a duty to keep a record of the certified schedule."
6.17 There
have been reservations expressed over this proposed requirement for
certification by the Authorised Person of the schedule of specifications. The
view is that it is not the practice for the Authorised Person of the development
project to certify a schedule of specifications for mock-up flats. The
developer specifies the fittings and finishes and the Authorised Person must
follow the specifications provided by the developer.
6.18 We take the
view that even with disclosure in the sales brochure, certification by the
Authorised Person is necessary. If the property is completed but prospective
purchasers are still not allowed to inspect it, they should have the same
protection as in the case of uncompleted properties. Once the units are
completed it is only necessary to certify that the mock-up units are the same as
the actual units.
|
Recommendation 17 We recommend that where there is no right of inspection before entering into a preliminary sale and purchase agreement and mock-up or sample flats are provided, the mock-up of at least one flat should be accurately representative of the actual unit in all aspects, including quality and dimensions. The Authorised Person of the development project should certify a schedule of specifications of such mock-up flats. The developer should have a duty to keep a record of the certified schedule. |
6.19 Purchasers of residential properties usually attach considerable
importance to the availability of communal facilities, such as a clubhouse and
swimming pool, and the present and future surroundings of the development.
Location and layout plans in the sales brochure are the major sources of
information on communal facilities and surroundings.
6.20 In the First
Report, the Commission considered that LOCM 101 (now replaced by LACO CM 40
which imposes the same disclosure requirements) provided a good model for the
provision of location and layout plans in sales brochures and recommended the
disclosure requirements be adopted for all uncompleted
units.[73] Unlike LOCM 101,
however, the Commission did not think developers should be required to state the
uses of land outside the boundaries of the development.
6.21 LOCM
101[74] (or LACO CM 40) requires
that the sales brochure of a Consent Scheme development should include:
"(i) a location plan 'including up-dated information on prominent environmental features in the vicinity eg public park, swimming pool, refuse collection point etc, intended user of surrounding areas, if known'; and
(ii) a layout plan drawn to scale 'including communal facilities (and their completion dates if possible); undeveloped land and its intended use within the boundary of the development; the scale used.'"
6.22 We
consider that the Commission's previous recommendations should be extended to
local completed flats. There have been queries as to the need to disclose the
intended uses of undeveloped land within the boundary of the development (as
required by LACO CM 40), on the grounds that it is difficult to show the
intended uses since intention can change subsequently. We take the view that
there is a case for stating the present intention even if that may change later.
In our view, there is a need for developers to disclose the intended and
permitted uses of land within the site of the development. At the end of the
day, it is important to educate the public on the need to check the land uses
carefully before making a decision to buy.
|
Recommendation 18 We recommend that : Location plan (a) A location plan should be provided in all sales brochures. The location plan should include up-dated information on prominent environmental features in the vicinity (eg public park, swimming pool, refuse collection point, etc). Layout plans All sales brochures should provide a layout plan drawn to scale, showing communal facilities (and their completion dates if possible) undeveloped land and its intended and permitted use within the boundary of the development, and the scale used. The layout plans provided in sales brochures should be the latest approved plans at the date of printing of the sales brochure. The expected completion dates of communal recreational facilities should be included in the layout plans. Uses of land (a) If there are specific covenants in the Government Lease requiring the developer to put land inside or outside the boundaries of the development to particular uses, the developer should state accurately those particular uses in the sales literature. |
6.23 Sales literature and advertisements sometimes contain misleading
artistic impressions. We have considered whether artistic impressions should be
prohibited, or whether they should be allowed but required to be accurate. It
is our view that artistic impressions of the surroundings of the building are
necessary for marketing purposes. Hence, we are of the view that artistic
impressions in whatever form should be allowed, but that they should give an
accurate representation of the surroundings of the property
development.
6.24 Two respondents to the consultation paper
expressed their support for our view that artistic impressions should
accurately represent the surroundings of the property
development.
6.25 One respondent, however, took the view that the
requirement of accurate artistic impressions could lead to many disputes in the
future and developers would find it difficult to comply with the requirement.
We do not anticipate that our proposal will create too many future disputes.
Whether or not an artistic impression is truly representative of the
surroundings is in most cases clear-cut. For instance, it cannot be disputed
that an artistic impression is inaccurate if it depicts a magnificent harbour
view whilst the development is in fact facing other
buildings.
6.26 Furthermore, with the aid of modern computer technology,
it is not difficult nowadays to create an artistic impression close to reality.
We have therefore decided to maintain the original recommendation.
|
Recommendation 19 We recommend that artistic impressions in whatever form should give accurate representations of the surroundings of the property development. |
6.27 Nowadays, in order to enhance their image as luxury apartments,
many developments, including those with only small and medium-sized flats, will
include a clubhouse and other communal facilities such as swimming pools, tennis
courts and children's playgrounds.
6.28 Whilst sales brochures usually
contain a general description of the clubhouse and the communal facilities, they
seldom mention with whom lies the responsibility for managing the day-to-day
affairs of these facilities. The result is that most purchasers will assume
that the developer or its subsidiary will manage the clubhouse and other
communal facilities in the long term. However, there are cases in which the
developer or its subsidiary assumes the management for the initial few years and
then hands over the managerial role to the owners themselves. Unless the owners
are well organised (such as by forming themselves into an owners' corporation),
they may not be prepared to take up the management of these facilities.
|
Recommendation 20 We recommend that the sales brochures should give the following details about the clubhouse and other facilities in the development: (i) whether they are communal facilities; (ii) who has ownership; (iii) who has responsibility for their management; and (iv) the duration of the management agreement. |
6.29 A completed unit is one with an occupation permit and, as such,
is only structurally in place but may not be fully fitted out with all the
fittings and finishes. An occupation permit can be issued upon the completion
of construction of the units and on general compliance with the requirements
relating to lifts, fire service installations and connection to the water
supply.[75] Buildings with an
occupation permit may not be ready for immediate occupation.
6.30 The date of completion can refer to any one of the following
dates:
(1) the construction completion date as stated in the formal ASP;
(2) the date of completion of sale and purchase; or
(3) the date of vacant possession.
6.31 The construction
completion date as stated in the formal ASP obviously has no relevance here as
we are dealing with properties for which the occupation permit has been issued.
The completion of the construction of the units is a pre-condition for the issue
of the occupation permit.
6.32 The date of completion of sale and purchase and the date of
vacant possession are of considerable importance to purchasers of completed
properties. The importance of these two dates is that they give purchasers an
idea as to when they are required to pay the balance of the purchase price and
when they can take possession of the property. Purchasers can then make their
accommodation and financial plans by reference to these two
dates.
6.33 When dealing with completed properties, the date of
completion of sale and purchase and the date of vacant possession are known with
certainty. It is therefore not difficult for developers to put these dates in
the sales brochure (or the price list). We understand that this is the existing
practice. However, in order to allow some flexibility the dates need not be
actual dates in the calendar. They can be a time frame, such as a certain
period of time from the signing of the formal ASP.
|
Recommendation 21 We recommend that all sales brochures should state the date of completion of sale and purchase and the date of vacant possession. The dates need not be expressed in terms of actual dates in the calendar. Instead, they can be expressed by reference to a time frame, such as a certain period of time from the signing of the formal ASP. We recommend that if any of the payment terms is dependent on the occurrence of a contingent event (such as execution of the assignment), the sales brochure or the price list should state the date of the happening of that event. |
6.34 For first-hand completed properties, the date of legal
completion is usually within five weeks of the preliminary
agreement.
6.35 The industry-wide practice is that where the original
purchaser sells the property on to a sub-purchaser, the developer and the
original purchaser would cancel their original agreement. The developer charges
an administration fee for the cancellation equivalent to one percent of the
consideration. The developer then signs a new agreement with the sub-purchaser.
The original agreement is cancelled. All additional costs so incurred will be
borne by the original purchaser or sub-purchaser. The required procedures and
administration fees charged by the developer for the cancellation of the
agreement are not always indicated clearly in sales brochures.
|
Recommendation 22 We recommend that where developers impose any fees or charges on transfer of title from the original purchaser to a sub-purchaser, or on the cancellation of the purchase agreement, the amount of such fees or charges and the procedures for transfer should be specified clearly in the sales brochure. |
6.36 We take the view that the public should be alerted to the
inherent risk in a confirmor sale. If a completed unit is re-sold to
sub-purchasers before the legal completion of the original sale, all
sub-purchasers will sign in the capacity as "confirmors" in the assignment. The
legal interests in the unit will pass from the developer direct to the
sub-purchaser at the end of the chain.
6.37 There is a risk that the
sub-purchaser at the end of the chain of sub-sales cannot get good title to the
property because of defaults of confirmors further up the chain. We are of the
view that in order to minimise the risk involved in sub-sales, all money should
be held by the solicitors as stakeholders.
6.38 We believe that, in
order to protect sub-purchasers, the Law Society should consider the
stakeholding of purchase monies in sub-sales and issue practice directions
requiring solicitors to warn purchasers of the risks inherent in confirmor
sales.
6.39 We also consider that the Estate Agents Authority
should require estate agents to remind purchasers of the risks involved in
confirmor sales.
6.40 In the case of local completed residential properties,
developers usually require the transaction to be completed within five weeks of
signing the preliminary agreement. Purchasers are therefore under some pressure
to arrange mortgage facilities. It is thus in purchasers' best interests that
sales brochures give them sufficient information as to the terms of the mortgage
loans that are offered by banks and other financial
institutions.
6.41 We have considered the recommendations in the First
Report and are of the view that they can be extended to local completed
residential properties, subject to some
modifications.[76]
|
Recommendation 23 We recommend that (a) Where the developer quotes in any sales literature or advertisement a list of banks providing initial finance, the sales literature should contain a general description of the finance schemes available from the banks so quoted. Where the interest is specified, it should be the rate per annum. |
6.42 There are invariably provisions in the formal ASP which give the
developer the right to charge interest on any part of the purchase price not
paid by the purchaser on its due date as set out in the agreement. The First
Report recommended that the rate of interest chargeable in those circumstances
should be included in the sales
brochure.[77] We take the view that
this recommendation should be extended to local completed residential
properties.
|
Recommendation 24 We recommend that the rate of interest per annum chargeable under the formal ASP for late payment of any part of the purchase price should be stated in the sales brochure. |
6.43 For completed properties, completion may not take place
immediately after signing of the preliminary agreement. There may still be a
time gap between the signing of the preliminary agreement and completion. In a
fluctuating market, banks may change their lending policies and refuse to grant
mortgage loans to the full extent they originally promised to the developer.
Purchasers will as a result fail to obtain the necessary amount of mortgage loan
to complete the transaction and their deposits will be forfeited. There is a
view that if a developer makes representations in the sales brochure or during
the promotion exercise as to the availability of mortgage facilities, the
developer should be liable if purchasers cannot subsequently obtain the
facilities. We do not share that view, as the developer has no control over any
subsequent change in bank lending policies.
6.44 Under the existing LACO rule, a purchaser of a Consent Scheme
flat is required to sign the formal ASP within three working days of signing the
preliminary agreement. He can withdraw from the preliminary agreement subject
to the forfeiture of five percent of the purchase price or the amount of the
preliminary deposit, whichever is the lower. The preliminary agreement is only
binding on the purchaser in respect of the forfeiture provision. It is
otherwise non-binding on the purchaser. The preliminary agreement is binding on
the vendor (ie the developer), however. We understand that this LACO rule
functions well and believe it can be applied to completed flats in the
first-hand market.
6.45 There is a view that developers should also be
entitled to the cooling-off period in the case of completed first-hand flats.
The reasoning is that after the units in a completed building are sold to the
public, the developer may occasionally receive an offer to buy the building,
either en-block or the majority of the completed units as an investment. It is
therefore not uncommon for developers selling first-hand completed properties to
make provision for cancellation of the agreement for purchase before completion.
We do not think it desirable that developers should also be entitled to the
cooling-off period. There are two reasons for this. Firstly, it is a departure
from the existing LACO rule, which stipulates that the preliminary agreement is
binding on the developer. The completed flats dealt with in this report are
largely uncompleted flats which have become completed with the issue of the
Occupation Permit. Hence, the LACO rule (which governs uncompleted flats)
should be followed in order to achieve consistency of treatment. Secondly,
nowadays most purchasers of completed flats are end-users rather than investors.
It would create too much uncertainty for end-users who have to make definite
accommodation plans if developers were allowed to cancel the preliminary
agreement after signing.
|
Recommendation 25 We recommend that if the preliminary agreement is binding as a sale, the purchaser should be entitled to a cooling-off period of three working days after signing the preliminary agreement for local completed residential properties in the first-hand market. A purchaser can elect to cancel the preliminary agreement within the cooling-off period subject to forfeiture of five per cent of the purchase price or the amount of the preliminary deposit, whichever is the lower. |
6.46 In Hong Kong, the usual procedure for the purchase of a
completed unit commences with the developer and the purchaser entering into a
preliminary agreement for sale and purchase (or a "Memorandum for Sale" as it is
more frequently called) at the site office or the developer's office. The
purchaser pays a deposit or reservation fee upon signing the preliminary
agreement. A formal ASP will later replace the preliminary agreement if the
purchaser decides to go ahead with the deal.
6.47 It is often difficult
to construe the terms in a preliminary agreement to determine whether it is
intended to be binding. It is therefore in consumers' interests that the sales
literature spell out whether or not the preliminary agreement is intended to be
binding.
6.48 If the preliminary agreement is not intended to be
binding, purchasers can walk out of the deal simply by not signing the formal
agreement within the stipulated period (usually within three working days of the
preliminary agreement). But there will, invariably, be legal consequences
following the purchaser's cancellation. It is desirable that sales brochures
should spell out these legal consequences, such as the amount of preliminary
deposits that would be forfeited. The procedures for rescinding the preliminary
agreement should also be stated in sales brochures. If the preliminary
agreement is to be rescinded by a formal cancellation agreement, there will be
legal costs such as the relevant solicitors' charges and Land Registry
registration fees. Purchasers should be informed of these costs in any sales
brochures.
6.49 We consider that the recommendations in the First Report
on this issue can be extended to local completed
flats.[78] A specimen copy of the
preliminary agreement should be displayed at the sales office.
|
Recommendation 26 We recommend that sales brochures should state that the preliminary agreement for sale and purchase is subject to a cooling-off period of three working days after signing the preliminary agreement. Sales brochures should also state that a purchaser can elect to cancel the preliminary agreement within the cooling-off period subject to forfeiture of five per cent of the purchase price or the amount of the preliminary deposit, whichever is the lower. |
6.50 Purchasers of first-hand completed flats from developers may not
be able to inspect the property until completion of the transaction. The
question is whether it should be mandatory for developers to allow prospective
purchasers to view the completed units before signing the preliminary agreement.
In our view, this question can be tied to the cooling-off period. Where a
purchaser has a right of inspection before signing the preliminary agreement and
he elects to cancel the transaction during the cooling-off period, the
preliminary deposits should be liable to forfeiture as mentioned above. If,
however, a purchaser does not have the right to inspect the unit before signing
the preliminary agreement, the preliminary deposit should not be liable to
forfeiture in the event of cancellation of the transaction during the
cooling-off period. Such arrangements have the advantage of encouraging
developers to allow purchasers to view the units before purchasers commit
themselves to a binding preliminary agreement. For the avoidance of doubt, a
purchaser who elects not to view the unit when offered the opportunity to do so
by the developer should be treated as if he has viewed the unit.
|
Recommendation 27 We recommend that if there is no right of inspection prior to signing of the preliminary agreement, the purchaser of a completed residential unit in the first-hand market should not be liable to forfeiture of his preliminary deposit where he takes advantage of the cooling-off period to cancel the preliminary agreement. |
6.51 There are two Defect Liability Periods, namely, (i) that which
applies between the developer and the purchaser, and (ii) that between the
developer and his contractor. Our concern is with the first of these periods.
Within the Defect Liability Period between the developer and the purchaser, the
purchaser may request the developer to make good any defects in the property and
its installations.
6.52 The current Defect Liability Period between the
developer and purchaser is in most cases six to 12 months from the date of
completion of the sale and
purchase.[79] Developers usually
require the purchaser to report, within 12 months of handing over possession,
any defects not ascertainable when the units are handed over. Any such
requirement, if stated in the formal ASP, can only limit the developer's
contractual duty to remedy defects but does not affect the developer's separate
liability in negligence to make good the defects. We consider that the
Defect Liability Period of completed units should run from the date of the
Assignment. By executing the Assignment, the purchaser becomes the legal owner
of the unit he has bought. It is therefore fair that the Defect Liability
Period starts to run from the date of the Assignment.
6.53 As the
duration of the Defect Liability Period is of great importance to
purchasers, we consider that sales brochures of local completed residential
properties should state the Defect Liability Period.
|
Recommendation 28 We recommend that sales brochure should state the duration of the Defect Liability Period and when it will start to run. |
6.54 There is a view that in order to provide better protection
for purchasers, the current Defect Liability Period of 12 months should be
lengthened to, say, 24 months as in the case of the Home Ownership Scheme. We
see no compelling reason to lengthen the current Defect Liability Period of 12
months. Most defects in the property will be detectable during the early months
of occupation. A common defect is blockage of pipes caused by decorators
dumping rubbish into the pipes. Such blockages are readily detectable. Another
common defect is water leakage, but this will normally be detectable during the
first complete annual cycle of seasons.
6.55 Most grantees of Government leases tend to be subsidiary shell
companies of developers. Some developers may evade their liability to make good
defects in the property by winding up the subsidiary shell company after
completion of the development. To address this problem, we consider that
recommendations should be made along the lines of observations made in the First
Report.[80]
|
Recommendation 29 We recommend that if the developer is wound up, the benefits of any warranties made to the developer by his contractors should be passed on to the Owners' Corporation or the Manager of the development. We recommend that, notwithstanding any term in the building contract between the developer and the contractor prohibiting the assignment of the developer's rights against the contractor, the purchasers should have the right to take direct legal action against the contractor for any defects in the units. |
6.56 The consultation paper considered the option of requiring
developers to provide bank bonds to cover defects. The bank bond might be, say,
one per cent of the construction costs. The consultation paper pointed out that
the disadvantage of a bank bond was that it would discourage small developers,
even though large developers might be willing to provide some sort of bond. On
the other hand, a bond was considered fair and worked well for projects in the
Housing Authority's Private Sector Participation Scheme.
6.57 Two
respondents to the consultation paper were in favour of the idea of requiring
developers to provide bank bonds to cover defects in the property. However,
another respondent expressed reservations at such an idea because of the
practical difficulties of its implementation, though the respondent did not
elaborate on the nature of these difficulties. It was suggested that, instead
of the provision of bank bonds, developers could be required to arrange for
insurance coverage for up to one year to cover the costs of rectifying defects
found after the liquidation of the developers and/or the
contractors.
6.58 As the provision of bank bonds by developers is a
complex subject and there are divided views on its feasibility, we have decided
to leave this issue to the Government for further exploration.
6.59 To prospective purchasers of local completed residential
properties, the Deed of Mutual Covenant (DMC) is an important document. A DMC
serves three main purposes. First, it has a technical purpose: the allocation
of shares in land. In Hong Kong, when a person buys a unit he buys the notional
shares, (called undivided shares) of the land. The DMC allocates units to the
undivided shares. The method of allocation can usually be found at the end of
the DMC. Whilst a purchaser buys the undivided shares allocated to his unit, he
also buys the exclusive use of his unit together with an equal share of the use
of the common parts.
6.60 The second purpose of a DMC is the definition
and regulation of rights between owners. The local laws and rules of the
development are achieved mainly through covenants binding all owners among
themselves and their successors. The covenants in relation to the common areas
and facilities are of particular importance.
6.61 The third purpose of a
DMC is to provide for management of the development. Usually, the management
rules are in the DMC, rather than a separate management agreement.
6.62 The parties to a DMC are normally the developer/vendor, the
first purchaser of a unit and the management company. As there is typically no
separate legal representation for the first purchaser, there is no negotiation
on the terms of the DMC.
6.63 The primary responsibility for settling the contents of the DMC
lies with the developer's solicitors. DMCs are similar in terms because of
Government's input and control. The Government, as grantor of land, imposes
certain conditions to protect purchasers of units. The LACO, for example, lays
down certain terms for DMCs relating to properties under the Consent Scheme. In
addition, the Building Management Ordinance (Cap 344) contains in two of its
schedules certain implied terms for DMCs. Most of these implied terms concern
management budgets, appointment and removal of the manager and meetings of
owners.
6.64 At present, detailed provisions on the management of
multi-storey buildings are contained in the two schedules to the Building
Management Ordinance (Cap 344). Cap 344, however, does not contain
provisions setting guidelines for the DMC. Instead, Government enforces DMC
guidelines by administrative means through the Consent Scheme. We are of the
view that the DMC guidelines require statutory backing because they are
currently applicable to Consent Scheme properties only. We consider that the
Government should set up a Building Management Working Group with a view to
providing a statutory basis for the DMC guidelines. One respondent
expressed support for this idea and considered that such a move would better
protect property owners, both as among themselves and in relation to
developers.
6.65 The First Report recommended that certain specified provisions
in the DMC should be disclosed in the sales brochures of local uncompleted
flats.[81] These were regarded as
the salient provisions.
6.66 What provisions of the DMC are salient,
however, may vary from development to development, and may change over time.
For example, modern technology has brought split-type air-conditioners which are
installed on the external wall. That may be in breach of the DMC, but was never
anticipated when the original DMC was drafted. The features of individual
developments are so varied that it would be difficult to draw up a universally
applicable list of salient features in the DMC.
6.67 We take the view,
however, that certain categories of provisions should be included in the list.
In the first place, clauses in the DMC imposing financial obligations are
generally of importance, as are those clauses touching upon everyday usage of
the property, such as recreational facilities, use of common areas, illegal
alterations and structures, prohibition on keeping of pets and
car-parking.
6.68 We consider that the salient provisions should be
disclosed in the sales brochures, and think that the Administration is best
placed to draw up a detailed list of the salient provisions of the DMC. In
doing so, we believe that the salient provisions in the Consent Scheme should be
used as a reference point.
|
Recommendation 30 We recommend that sales brochures should state the salient provisions of the Deed of Mutual Covenant (DMC). The list should include those clauses in the DMC imposing financial obligations and those touching upon everyday usage of the property. |
6.69 The First Report recommended that sales brochures should state
that English and Chinese versions of the DMC are available at the sales office
or solicitor's office for
inspection.[82] That recommendation
would oblige the developer to arrange for Chinese translation of the DMC. We
take the view that it is desirable to have a Chinese version of the
DMC.
|
Recommendation 31 We recommend that the developer should deposit copies of the English and Chinese versions of the DMC at the sales office or the solicitors' office for free inspection during normal office hours. The sales brochure should contain a statement to the effect that the English and Chinese versions of the DMC are so available for inspection. |
6.70 The slope adjacent to a building is often owned by individual
owners of the building under the terms of the Government Lease. The maintenance
of these slopes is the responsibility of the individual owners. The DMC often
sets out the individual owners' liability for potential expenses for maintenance
of slopes or other areas. The consent letter issued by the LACO will build such
a provision into the DMC (called a Slope Maintenance clause) to ensure that
money can be collected in future from owners to undertake the repairs or
maintenance.
6.71 The cost of maintaining and repairing slopes or other
areas can be great and the burden on individual owners heavy. As heavy rains
are common every summer, slopes are liable to erosion and damage. It is
important that purchasers know of that potential liability for maintenance of
slopes or other areas.
|
Recommendation 32 We recommend that if there is actual or potential responsibility for maintaining slopes or other areas, there should be clear notification to purchasers in the sales brochure of that responsibility. The sales brochure should also disclose any existing notice from the authorities to repair and maintain slopes or other areas at the date of its printing. Moreover, if there is responsibility in the Government Lease for maintaining slopes or other areas, that responsibility should be spelt out in the sales brochure. |
6.72 We take the view that if an uncompleted development has a DMC,
developers should have an obligation to keep its terms unchanged when it later
becomes completed with the issue of the occupation permit. The contents of the
DMC should not change because it defines the rights and obligations of the
owners in the same development. Whether or not there is an occupation permit
should not have any bearing on those rights and obligations.
|
Recommendation 33 We recommend that if an uncompleted development has a DMC, developers should have an obligation to keep its terms unchanged when the development later becomes completed with the issue of the occupation permit. |
6.73 There are three main areas of concern in relation to the
conditions of the Government lease: (i) user restrictions; (ii) duration; and
(iii) special lease conditions. User restrictions are the most important
conditions of the Government lease.
6.74 Government leases and Conditions of Grant contain provisions
which restrict the land to certain uses, the common ones being
"commercial/residential", "non-industrial" and "industrial/godown". Compliance
with the user restrictions is important as the Government may re-enter and take
back possession of the land if a condition governing the land use is breached.
Moreover, if the land is put to more valuable use than that specified, a premium
has to be paid to the Government. If, for example, an industrial use is
converted to residential, a premium equal to the difference between the market
value of the two uses will be payable.
6.75 The duration of the Government lease and the unexpired term of
the lease are of interest to purchasers because renewal of a Government lease
requires a substantial increase in the annual rent payable to the Government.
The amount of Government rent in some cases could be three per cent of the
rateable value of the property[83]
and that can be a substantial sum. It is the responsibility of the individual
owners to pay their share of Government rent of the lot where the building is
situated.
6.76 Apart from the potential liability for Government rent,
the duration of the Government lease and its unexpired term are of interest to
purchasers because it may affect banks' mortgage policies for the
development.
6.77 There are various special lease conditions which impose on a
flat-buyer continuing financial obligations, including:
(1) The construction and maintenance of pedestrian subways and footbridges;
(2) The construction and maintenance of escalators, stairways and lifts for the disabled;
(3) The maintenance of slopes, toe-walls and retaining walls;
(4) The maintenance of private open spaces and toilets; and
(5) The maintenance of internal roads.
6.78 The First
Report made certain recommendations in relation to the conditions of the
Government Lease.[84] We consider
that those recommendations can be extended to local completed residential
properties.
|
Recommendation 34 We recommend that sales brochures should state the following: (1) the permitted uses of the individual units as stated in the approved building plans, together with any restrictions on use contained in the Government lease or Conditions of Grant of the land; Sales brochures should also contain a general notification to the effect that the Government lease will impose various financial obligations on purchasers and that they are advised to consult their professional advisers accordingly. These financial obligations include: (a) the construction and maintenance of pedestrian subways and footbridges; |
6.79 Whilst we consider it desirable that the Government lease should
be translated into Chinese, we are aware that there are few available resources
for the translation work and problems can arise as to who should be responsible
for the costs of translation. Bearing in mind these practical difficulties,
we consider that it would be desirable for the Government to prepare a
summary of extracts of the Government lease in plain language, in both English
and Chinese.
6.80 Some property owners have complained that some solicitors when
acting for a purchaser do not check whether Government rent is paid up to date
before completing a sale and
purchase.[85] As the new Government
rent may involve greater sums of money, it is important that property owners are
not exposed to additional charges which should have been the responsibility of
the previous owners. There is the possibility of re-entry by Government in the
event of non-payment of Government rent, even if the amount is small. We
consider that the Law Society should encourage solicitors to properly apportion
the respective liabilities of vendor and purchaser to pay Government rent at the
time of conveyancing.
6.81 The First Report made several recommendations to ensure
prospective purchasers of uncompleted properties obtain an accurate impression
of the prices of the units offered for sale and their
number.[86] Those recommendations
were made on the basis that prospective purchasers had to go through the process
of balloting in all public sales. Nowadays, balloting is seldom used in the
sale of completed units in view of prevalent market conditions. Depending upon
market conditions, discounts from the prices quoted in the price lists are
sometimes offered. When estate agents are employed by the developer to
negotiate with prospective purchasers, price lists sometimes are not released to
the public. In such situations, purchasers are not aware of the true prices
being offered by the developer.
|
Recommendation 35 We recommend that the price lists of all units offered for sale should be made available to prospective purchasers by developers or their estate agents prior to the payment of any reservation fee or the signing of any preliminary agreement. We recommend that if developers advertise that a certain number of units will be offered for sale, that number of units should be available for sale to the public. |
6.82 The First Report made a number of miscellaneous recommendations
as to information which should be included in sales brochures for local
uncompleted flats.[87] These
included the names of the contractors and Authorised Persons, responsibility for
transaction fees, the date of printing of the sales brochure, supplementary
charges payable by purchasers on taking possession, licence fees payable to
Government, charges for rights of way, and details of car park spaces. We
consider similar recommendations should be made in respect of local completed
units. In addition, we take the view that the name of the firm of the
Authorised Person should be stated. Prospective purchasers may show more
interest in the name of the firm than the identity of the individual Authorised
Person.
|
Recommendation 36 Name of main contractors, Authorised Person and his firm We recommend that the names of the main contractors and the Authorised Person and his firm should be disclosed in the sales brochure. For present purposes, the Authorised Person means the person occupying that position at the time of printing of the sales brochures. |
|
Recommendation 37 Responsibility for transaction fees We recommend that whenever the sales brochure contains information about the prices of the units, it should also state with whom the responsibility for legal costs and stamp duties lies. Scales of legal costs and stamp duties We recommend that information on the scales of legal costs (if any) and stamp duties should be provided by developers to purchasers upon request and a note to this effect should appear in the price list or other sales literature containing information about the prices of the units. Date of printing of sales brochure We recommend that the sales brochure should carry its date of printing. Supplementary charges upon taking possession We recommend that the sales brochure should provide an itemised list of supplementary charges payable by purchasers upon taking possession of their units. If the exact amounts of such charges are unknown, the obligation to pay them should be disclosed in the sales brochure. Licence fees to Government and charges for rights of way We recommend that where applicable, the sales brochure should state any way leave charges, licence fees or waiver fees payable to Government for a water supply or drainage system going through Government land and/or pump room situated on Government land and any fees or charges payable to adjoining lot owners for rights of way or easements. The amount of such charges or fees should also be stated, if known. |
|
Recommendation 38 Car park spaces We recommend that the sales brochure should contain a description of the car park spaces within the development, including their respective numbers for sale or rent, and those for visitors. If the developer has not yet decided at the date of the printing of the sales brochure any of these matters, the sales brochure should clearly state this fact. Moreover, any descriptions of car park spaces in the sales brochure should be binding on the developer. |
6.83 The Sub-committee identified three alternative ways of applying
their recommendations to local completed flats offered for sale by developers in
the first-hand market. These were:
(1) voluntary compliance by developers;
(2) Government encouraging good market practices, while actively continuing to look into the need for legislation; and
(3) legislation.
The Sub-committee was unable to reach an
agreed view as to which of these alternatives should be pursued and left this
question for the Commission to decide. We have unanimously concluded that the
recommendations in this report in respect of the first-hand market should be
implemented by legislation. We consider below the case for and against each of
the three options.
6.84 The principal advantage of a scheme of voluntary compliance is
that it could, if the industry agreed, be implemented more speedily than formal
legislation. The likely mechanism to achieve compliance would be for the Real
Estate Developers Association (REDA) to draw up guidelines based on this
report’s recommendations. Developers’ compliance with the
guidelines could be encouraged by establishing a system for recording and
resolving complaints, and by programmes of consumer education. Those who favour
this approach argue that a developer who did not comply with the guidelines
would be viewed negatively in the market, and this would be damaging in present
market conditions.
6.85 We do not find this alternative attractive, nor
the arguments in its favour persuasive. The most obvious shortcoming is that it
provides no effective sanction against those who fail to comply with the
guidelines. Not all developers are REDA members, and even for those which are,
REDA’s only sanction would be expulsion of the errant developer from
membership. That is an option which it is unlikely REDA would wish to pursue.
More importantly, our recommendations are designed to offer greater protection
to purchasers of completed residential properties, yet a voluntary scheme based
on guidelines established by developers provides no assurance that
consumers’ interests will prevail. The guidelines could be amended at any
time by the industry without taking account of consumer input.
6.86 It
is true that we are proposing that there should be voluntary compliance in the
second-hand market, but that can be readily distinguished from the position in
the first-hand market where the vendor and purchaser are not generally on an
equal footing. Voluntary compliance was rejected in both the First and Second
Reports. It was pointed out in the First Report that “it would be
difficult to control developers who chose to ignore the
code”[88] and in the Second
Report that, “as a code of practice does not have the force of law, it
cannot be expected to be an effective tool of
regulation”.[89] We adhere
to that reasoning, and reject voluntary compliance as an effective option in
respect of completed residential properties in the first-hand market. We note
that there has been movement towards self-regulation by the industry in respect
of the recommendations contained in our First Report, but are cognizant of the
fact that those developments were prompted by the Administration’s
publication of draft legislation. Finally, it is difficult to see why
developers should be expected to adopt voluntary guidelines if they object to
the same standards being applied by legislation.
6.87 Under this option, the Government should take immediate steps to
promote good market practices based on the recommendations in this report. The
Government should continue to consider the legislative option and move to
implement this if compliance proves unsatisfactory. The only features which
distinguish this from the first option are that it would be the Government
rather than the industry itself encouraging compliance, and the option of
legislation would remain a viable alternative. The principal argument in favour
of this option is that, like the option of voluntary compliance, it could be
implemented more speedily than legislation. The possibility of legislation at
some future date might prove effective in persuading the industry to comply
voluntarily.
6.88 Again, we find this option unconvincing. While
Government persuasion may garner some success, it is difficult to see how the
Government could hope to promote good market practices among developers of
Non-Consent Scheme developments as they do not need to obtain the
Government’s consent before selling their flats. Even in Consent Scheme
cases, the consent conditions will no longer apply once the developers have
obtained the Consent to Assign or the Certificate of Compliance. The imminent
threat of legislation may be effective in achieving self-regulation, but we do
not think it likely that the possibility of legislation at an unspecified future
date would achieve much. We accordingly reject this alternative.
6.89 The introduction of legislation to implement the recommendations
in this report has the disadvantage that it will inevitably take time to
achieve. However, in our view this option presents the most effective way of
ensuring compliance. It enables realistic sanctions to be applied to those who
fail to observe the terms of the scheme and offers proper protection to
consumers. The standards applied will be uniform across the industry, and not
merely among REDA members, or those who choose to comply.
6.90 It has
been asserted by some that legislation in this area presents insurmountable
technical difficulties, or will be unduly inflexible. We do not believe either
of these objections is valid. While the drafting of the legislation will
undoubtedly require care and consideration, there is no reason to suppose that
the particular circumstances of the property industry are so unique as to defy
the expertise of the draftsman and the legislature. Equally, flexibility can be
built into the legislation by confining the principal Ordinance to the basic
ambit of the scheme, while incorporating the detailed provisions in subsidiary
legislation. The subsidiary legislation can be amended relatively easily should
changes prove necessary at a later stage in the light of
experience.
6.91 We accordingly conclude that our recommendations in
respect of the first-hand market should be implemented by
legislation.
|
Recommendation 39 We recommend that our recommendations in respect of the first-hand market should be implemented by legislation. |
6.92 The First and Second Reports concluded that there should be both
criminal and civil sanctions against those who failed to comply with the
proposed legislation. We think that a similar approach is appropriate in
respect of the legislation which implements the recommendations in this report.
We note that the White Bill published by the Housing Bureau in April 2000 to
implement the recommendations in our First Report proposed that failure to
provide a sales brochure containing the information specified in the legislation
should result in a fine of $5 million on conviction on indictment, or $100,000
on summary conviction. Where the dimension of any part of a sample property
differs from the information stated in the notice displayed in the sample
property, a fine of $1 million on conviction on indictment, or $100,000 on
summary conviction, was
proposed.[90] The White Bill also
prescribed penalties for a number of other breaches. We think that the
determination of an appropriate level of penalty is one more appropriately left
to the Administration, but we would reiterate the view expressed in the First
Report that the maximum fine for an offence under the proposed legislation must
be substantial enough to achieve the necessary deterrent effect.
6.93 As
far as civil remedies are concerned, we confirm the approach favoured in the
First Report[91] and recommend the
creation of a statutory tort for breach of the legislation. The purchaser
should be able to claim damages for loss suffered as a result of a breach of the
proposed legislation. The remedies available under the new tort should be
confined to damages, however, and rescission should not be available. In making
this recommendation, we echo the First Report’s view that purchasers would
not normally wish to rescind the purchase agreement, except in a falling market.
In such a market, rescission would give purchasers the chance to rescind the
transaction for minor breaches which may not go to the heart of the
contract.
6.94 As with the recommendation for the creation of a
statutory tort contained in the First Report, we do not intend that the existing
remedies available under the formal ASP should be diminished in any
way.[92] The intention is that
purchasers would be given additional remedies for breach of the proposed
legislation. There will be overlap, but we consider that there should be clear
provisions in the new legislation that nothing in that legislation will detract
from the rights of the purchaser under the formal ASP, and that no clauses in
the ASP will detract from the statutory remedies in the legislation. This
approach was followed in the White Bill, which provided that the relevant
provisions in the legislation “shall not prejudice any right of, or remedy
available to, a purchaser of an uncompleted property arising otherwise”
than under those
provisions.[93]
|
Recommendation 40 There should be both criminal and civil sanctions against those who fail to comply with the proposed legislation. We consider that the determination of the appropriate level of criminal penalty is a matter for the Administration to decide, but the maximum fine should be substantial enough to act as an effective deterrent. We recommend that a breach of the proposed legislation should constitute a statutory tort. Purchasers should be able to claim damages for loss suffered as a result of a breach of the proposed legislation, but rescission should not be an available remedy. There should be clear provision in the new legislation that nothing in that legislation will detract from the rights of the purchaser under the formal ASP, and that no clauses in the ASP will detract from the statutory remedies in the legislation. |
[67] See paragraph 2.19 of
the First Report for the previous recommendations on floor
plans.
[68] The First Report, at
paragraph 2.20.
[69] The First
Report, at paragraphs 3.14 to 3.17.
[70] Subsequently on 21 July
1999, the Legal Advisory and Conveyancing Office Circular Memorandum No 40A
(LACO CM 40A) was issued. LACO CM 40 remains valid and in place except so far
as modified by LACO CM 40A (paragraph 4 of LACO CM 40A refers). LACO CM 40A
deals with balloting and exemption from registration and has no substantial
effect on the proposals in this report.
[71] The First Report, at
paragraph 3.19.
[72] The First
Report, at paragraph 3.24.
[73]
The First Report, at paragraphs 4.19 to 4.25.
[74] See Appendix 1 of Land Office Circular Memorandum No 101, at paragraphs A 2 & 3. The same requirements are contained in paragraphs 2 and 3 of Appendix XII of Land Advisory Conveyancing Office Circular Memorandum No 40 which came into force on 28 May 1999.
[75] See section 21(6) of
Buildings Ordinance (Cap 123) which spells out the circumstances in which an
application for an occupation permit will be refused by the Building
Authority.
[76] See the First
Report, at paragraphs 7.6 to 7.8 for the previous
recommendations.
[77] The First
Report, at paragraph 7.10.
[78]
The First Report, at paragraphs 8.5, 8.6 and 8.13.
[79] In the Housing Authority's
Private Sector Participation Scheme, the Defect Liability Period is
12 months from the date of the Assignment. Starting from Phase 17A in
1995, the Defect Liability Period of Home Ownership Scheme units has changed to
12 months from the date of the completion
certificate.
[80] The First
Report, at paragraphs 17.5 and 17.7.
[81] These were: (1) The
definition of common parts; (2) the number of undivided shares allocated to each
unit and the method of apportionment of management charges; (3) the fact that
the number of undivided shares is subject to change; (4) the sum payable by the
owners as deposit for the first year budgeted management expenses (to be
expressed in terms of a specific number of months of management fee if the exact
amount has not yet been worked out); (5) any restrictions imposed on owners in
the use of the common parts; (6) interest and charges on owners who default in
paying sums due under the DMC; and (7) the name of the first manager (if already
decided) and the minimum period of its management. See paragraph 10.13 of First
Report.
[82] The First Report,
at paragraph 10.15.
[83] Non-renewable Government Leases which expire before 30 June 1997 are automatically extended up to 30 June 2046 without payment of additional premium but a new Government rent is payable (see Annex III of the Sino-British Joint Declaration on the Question of Hong Kong). All Government Leases whether in Hong Kong Island, Kowloon or the New Territories which have been granted since 27 May 1985 are also subject to this new Government rent from 1 July 1997 (see paragraph 1 of explanatory notes to Preliminary Advices on Government Rent issued by the Rating and Valuation Department to individual owners in April 1997.) The result is that many new developments are subject to the new Government rent, as they are built on lots of land granted after 27 May 1985. The new Government rent is at three percent of the rateable value of the property and so can be a substantial sum. This being the case, the Rating and Valuation Department has since 1 July 1997 issued demands for Government rent to the individual owners who are so liable.
[84] The First Report, at paragraphs 11.12 to 11.13.
[85] See Legal Advisory and
Conveyancing Office Circular Memorandum No 22 dated 30 September
1996.
[86] First Report, at
paragraphs 12.6, 12.15 and
12.16.
[87] First Report, at
paragraphs 13.7, 13.13, 13.14, 13.18, 13.22, 13.24,
13.29.
[88] The First Report, at
paragraph 15.3
[89] The Second
Report, at paragraph 11.2
[90] Consultation Paper on
the Sales Descriptions of Uncompleted Residential Properties Bill, at page
6.
[91] The First Report, at
paragraph 15.16
[92] The First
Report, at paragraph 15.21
[93] Consultation Paper on the Sales Descriptions of Uncompleted Residential Properties Bill, at clause 6(4) of the Bill.