PNEUMOCONIOSIS AND MESOTHELIOMA (COMPENSATION) (ASSESSMENT OF LEVY) REGULATIONS - REGULATION 6H
Time limit on imposing surcharge: construction operations other than those under term contract
(Past version on 01/01/2008).
In respect of construction operations other than those carried out under a
term contract, a surcharge may not be imposed after the expiry of whichever is
the last to end of the following periods—
(a) 2 years after the completion of the construction operations;
(b) one year after evidence, sufficient in the opinion of the Board to
justify the imposition of the surcharge, comes to its knowledge.
(12 of 2006 s. 84)