BUILDING (ADMINISTRATION) REGULATIONS - REGULATION 26

Certificate to be given by registered contractor and authorized person on completion of street works

(Past version on 07/11/1997).
(Past version on 30/06/1997).

(1) Within 7 days of the completion of any street works in respect of which he
has been appointed, the registered general building contractor or the
registered specialist contractor shall, in the specified form, certify that
such works have been carried out in accordance with the provisions of the
Ordinance and regulations and shall, within the said 7 days, deliver such
certificate to the authorized person appointed in respect or the street works.

(2) Within 14 days of the completion of any street works in respect of which
he has been appointed, the authorized person shall, in the specified form
delivered to him, in accordance with paragraph (1), by the registered general
building contractor or the registered specialist contractor appointed in
respect thereof, certify that such works have been carried out in accordance
with the plans approved in respect thereof by the Building Authority and
shall, within the said 14 days, send such certificate to the Building
Authority. (L.N. 188 of 1974; L.N. 347 of 1993; L.N. 514 of 1997)