Total value of construction operations

(1) For the purposes of this Ordinance, “total value” (總價值), in
relation to construction operations carried out under a construction contract,
means—

   (a)  if the contract is a term contract under which works orders are
        issued, the aggregate of the values of all construction operations
        carried out as required by those works orders;

   (b)  if the contract is not a term contract described in paragraph

   (a)  , but a contract under which the construction operations are or form
        part of any construction operations that are carried out in stages,
        the aggregate of the values of all stages of the construction
        operations so carried out; and

   (c)  in any other case, the value of the construction operations.

(2) For the purposes of this Ordinance, “total value” (總價值), in
relation to construction operations that are not carried out under a
construction contract, means—

   (a)  if the construction operations are or form part of any construction
        operations that are carried out in stages, the aggregate of the values
        of all stages of the construction operations so carried out; and

   (b)  in any other case, the value of the construction operations. “total
        value” (總價值)